News / Challenging conditions at sea delay Balticconnector’s inspections

Challenging conditions at sea delay Balticconnector’s inspections

Gasgrid Finland and the Estonian gas transmission system operator Elering AS noticed an unusual drop in pressure in the Balticconnector offshore gas pipeline that runs between the countries on the small hours of October 8, 2023. The pipeline was isolated shortly after the discovery by closing Balticconnector’s valves. Due to the unusual drop in pressure, it was reasonable to suspect that the cause of the incident was damage to the pipeline and a resulting leak. The gas leak caused by the verified damage in the pipeline has stopped due to the isolation of the pipeline and the closing of the valves. At the moment, gas transmission between Finland and Estonia has halted. The state of the Finnish gas system is stable, and the supply of gas is secured via Inkoo LNG floating terminal.

On Tuesday, Finnish authorities confirmed the suspected damage to Balticconnector, which caused an unusual drop in pressure observed in the early morning of Sunday 8 October. Gasgrid Finland’s previously launched offshore pipeline inspection operation continues, despite the findings, to cover other sections of the pipeline. The goal of the ongoing inspection operation is to get an accurate understanding of the condition of the entire offshore pipeline, after which planning for more detailed repair measures and their schedule can be started. Gasgrid Finland is responsible for the inspection operation, and it is carried out in cooperation with Elering. The inspection operation has been underway this week. Due to the challenging conditions at sea, the inspections will continue next week as well and are expected to be completed by the end of next week.

Based on preliminary expert assessments, it can be assumed that the planning of the repair work, the mobilization of the necessary underwater equipment and the actual repair measures, including the inspection of the repaired pipe section and commissioning, will last at least five months. Therefore, the earliest possible commissioning date of the Balticconnector -pipeline would be at the beginning of April 2024.

The state of Finland’s gas system is stable and the supply of gas is secured

The situation of the Finnish gas system is stable, and the supply of gas from the LNG terminal in Inkoo has been secured. The terminal has the capacity and the ability to deliver the gas Finland needs, including in the coming winter, even though gas consumption is typically higher in winter seasons. Market players have been instructed to ensure the gas supply they need by ordering it to Inko or the Hamina LNG terminal, so that the continuity of the gas supply is secured in the coming winter season.

Gasgrid will inform more about the development of the situation on its website www.gasgrid.fi as soon as more information is available.

More information:

Janne Grönlund, SVP, Transmission System, Gasgrid Finland Oy, +358 40 036 8825

Media contacts: Virve Wright, SVP, Communications, Sustainability, Public Relations, Gasgrid Finland Oy, +358 40 552 9219

Gasgrid is a multi-gas company of the future providing energy transmission system solutions to promote clean transition and an energy-efficient society. We strengthen Finland’s economic growth, security of supply, and energy independence, and support the balancing power required for emission-free electricity production. Through our international infrastructure projects, we are preparing to meet the demand for clean gas energy in Europe as well. Gasgrid Group’s business operations consist of gas operations, LNG terminal operations, hydrogen development, and project execution. More information: gasgrid.fi/en

Share:

Privacy Overview
Gasgrid

This website uses cookies so that we can provide you with the best user experience possible.

Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.

Strictly Necessary Cookies

Strictly Necessary Cookies are part of the core functionality and this site might not work correctly without them. For example the language selection and answer to this cookie consent are stored in these cookies. All cookies can be disabled from the browser settings or with a browser extension.

Analytics

Analytics cookies are used to collect anonymous site usage data. The cookie allows tracking the user's movements between different visits, but not the identification of an individual user.

We use Google Analytics to analyse and track the use of our online services. Usage data is collected through cookies, but the data is not processed or stored in a way that would allow tracking the usage of an individual user.

The information is used to improve the user experience on our website and to track the number of visitors on the website.