Floating LNG Terminal Finland Oy, a 100 % subsidiary of Gasgrid Finland Oy, as the terminal operator for the FSRU (Floating Storage and Regasification Unit) vessel Exemplar, moored in the port of Inkoo since December 2022, announces that all available Spot Slot Capacity for the period 14 December until 6 April was reserved during the capacity allocation and Annual Service Schedule will be updated accordingly in the next Monthly Update.

Due to the allocation being quite congested, Congestion Management according to Terminal Rules clause 8.4 was applied to allocate available capacity. All slots now allocated for 14 December, 2023 until 6 April, 2024 will be under temporary Joint Use Rules approved by Energy Authority applying Joint use for the full period. Said Slots will also be invoiced on actual discharged cargo quantity for this period to aid operational predictability and flexibility for the winter period. No other changes to the current Terminal Rules will be applied for the period and no update to the current Terminal Rules will be issued as these changes are temporary.

Currently all slots at the Inkoo LNG Terminal are booked for the current Gas Year. However, Floating LNG Terminal Finland Oy will reserve the right to open Reduced Capacity Late Spot Slots for Winter 2023/2024. The size, and flexibility, of these Slots will be defined in each invite and can generally be up to around 500 GWH and will be offered on a need basis. Late Spot Slot conditions will be applied to these Reduced Capacity Late Spot Slots, and Joint Use will therefore not be applicable to these. The LNG delivered during these slots will have to be withdrawn according to the regasification period defined in the invite.

Gasgrid is a multi-gas company of the future providing energy transmission system solutions to promote clean transition and an energy-efficient society. We strengthen Finland’s economic growth, security of supply, and energy independence, and support the balancing power required for emission-free electricity production. Through our international infrastructure projects, we are preparing to meet the demand for clean gas energy in Europe as well. Gasgrid Group’s business operations consist of gas operations, LNG terminal operations, hydrogen development, and project execution. More information: gasgrid.fi/en

Share:

Privacy Overview
Gasgrid

This website uses cookies so that we can provide you with the best user experience possible.

Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.

Strictly Necessary Cookies

Strictly Necessary Cookies are part of the core functionality and this site might not work correctly without them. For example the language selection and answer to this cookie consent are stored in these cookies. All cookies can be disabled from the browser settings or with a browser extension.

Analytics

Analytics cookies are used to collect anonymous site usage data. The cookie allows tracking the user's movements between different visits, but not the identification of an individual user.

We use Google Analytics to analyse and track the use of our online services. Usage data is collected through cookies, but the data is not processed or stored in a way that would allow tracking the usage of an individual user.

The information is used to improve the user experience on our website and to track the number of visitors on the website.